Section 126
Reward May Be Given To Those Who Complete Work Prior To Time
(1) It may be provided that the public entity may reward the construction entrepreneur who completes the work prior to the period specified in the procurement contract.
(2) The amount of reward referred to in sub-rule (1) shall be determined on the basis of sub-rule (3) for such a number of days by which the work was completed before the period specified in the procurement contract.
(3) While determining the rate referred to in sub-rule (2), the rate shall be so determined as equivalent to the same amount that the construction entrepreneur has to pay as liquidate damages to the public entity on daily basis for failure to complete the work within the period specified in the procurement contract.
(4) Notwithstanding anything contained elsewhere in this Rule, the total amount of reward shall not exceed ten percent of the contract price.